Skip to content
Electric Cooperative

Battery Storage Peak-Shaving Deployment Cuts Demand Charges 19 Percent

The Archive Co designed and commissioned a 20 MW / 80 MWh battery storage system for CoastalGrid Cooperative, reducing wholesale demand charges by 19 percent in the first full year of operation.

19%

Demand Charge Reduction

20 MW / 80 MWh

System Size

All but 1

Peak Events Avoided

9 months

Commissioning Duration

The Problem

CoastalGrid Cooperative, a member-owned electric cooperative, faced rising wholesale demand charges driven by a small number of annual peak demand events, but lacked the generation capacity or budget for conventional peaking capacity to manage those events.

The cooperative's board needed a capital-efficient solution that member ratepayers could clearly see delivering value, given the cooperative's transparent, member-governed capital approval process.

Our Solution

The Archive Co conducted a detailed load analysis to size a battery storage system specifically against the cooperative's actual historical peak event profile, rather than a generic capacity sizing rule of thumb, to right-size the investment against realistic demand charge exposure.

We led vendor selection and full technical specification for a 20 MW, 80 MWh LFP battery storage system, and provided owner's engineer oversight through commissioning, including validation of the dispatch algorithm against the cooperative's actual tariff structure.

Our team also developed a clear, board-ready return on investment tracking framework so cooperative leadership could report concrete demand charge savings back to member ratepayers each year.

Timeline

Load Analysis & Sizing

5 weeks — peak event analysis, system sizing study

Vendor Selection & Specification

8 weeks — technical specification, vendor evaluation

Owner's Engineer Oversight

9 months — design review through commissioning

Results

  • Wholesale demand charges fell 19 percent in the first full year of system operation, directly attributable to the battery system's peak-shaving dispatch during the cooperative's highest-cost demand events.
  • The dispatch algorithm, validated against the cooperative's actual tariff structure during commissioning, successfully avoided all but one minor peak event in the first year, which was traced to an unusual weather-driven demand spike outside the system's original design assumptions and addressed through a dispatch logic update.
  • Board-ready ROI reporting supported the cooperative's decision to evaluate a second, larger storage deployment the following year.
Monthly Peak Demand Charge Before and After Deployment

Relative Index

Illustrative relative monthly peak demand charge comparison before and after the battery storage deployment.

Practice Area

Operations

Explore Operations